Project Timeline

Ryman Retirement Village, Havelock North

The following timeline shows the on-going progress of one of our current projects and our approach to the job.
Lead Contractor

Drainways was awarded lead contractor for all civil and town house drainage, earthworks, roading, surfacing, paving and topsoil on the $100 million Ryman Healthcare retirement village in Havelock North.

Mark Currie / Drainways Director

  1. Drainways|Timeline
    20 / September 2019

    Site entry being established

  2. Drainways|Timeline
    26 / September 2019

    Overview of site in first month.

  3. Drainways|Timeline
    01 / October 2019

    Haul roads being established and main building being excavated for pre-loading.

  4. Drainways|Timeline
    10 / October 2019

    Stormwater materials on site and starting to be installed.

  5. Drainways|Timeline
    17 / October 2019

    First of 3 Triton Stormwater Detention Tanks being installed.

  6. Drainways|Timeline
    28 / October 2019

    A good start to the pre-load for the main building.

  7. Drainways|Timeline
    11 / November 2019

    At the other end of the site – the first building pads being completed.

  8. Drainways|Timeline
    20 / November 2019

    South end of the site – services and building pads progressing well.

  9. Drainways|Timeline
    28 / November 2019

    20,000m3 of pre-load material completed on the main building and pre-load on apartment block underway.

  10. Drainways|Timeline
    09 / December 2019

    Several building pads completed ready to be handed over to builders.

  11. Drainways|Timeline
    18 / December 2019

    Pre-load on main and apartment building complete, building pad preparation on 2nd apartment underway.

  12. Drainways|Timeline
    10 / January 2020

    First frames standing and several building pads ready to box.

  13. Drainways|Timeline
    19 / January 2020

    Overview of site looking from North to South.

  14. Drainways|Timeline
    30 / January 2020

    Building pads and drainage being completed at North end of site.

  15. Drainways|Timeline
    18 / February 2020

    Permanent site office compound established and civil drainage happening at North end of site.

  16. Drainways|Timeline
    28 / February 2020

    Pre-load on main building starting to be removed.

  17. Drainways|Timeline
    19 / March 2020

    Birds eye view of complete site, pre-load removed from apartment building.

  18. Drainways|Timeline
    18 / June 2020

    Kerbs starting at south end of site.

  19. Drainways|Timeline
    21 / June 2020

    Meanwhile more house pads being prepared at north end of site.

  20. Drainways|Timeline
    09 / July 2020

    Kerbs and roading underway, all services to townhouses being installed and gardens planted.

  21. Drainways|Timeline
    07 / August 2020

    Roading, kerbs, topsoil, sub-soil drains being completed.

  22. Drainways|Timeline
    15 / September 2020

    First asphalt down, more topsoil and roading happening.

  23. Drainways|Timeline
    19 / October 2020

    South end of the site complete with grass, irrigation paving, planting and residents living in their homes.

Case Sudies

Other Projects

Our work is out of sight, but never out of mind.

The following projects are a showcase of our capabilities and approach to what we do.

Drainways|Timeline
Drinking Water

Frimley Park Water Treatment Plant, Hastings

Drainways|Timeline
Drinking Water

Te Mata Road Water Main Replacement, Havelock North

Drainways|Timeline
Stormwater

Links Road Roundabout Drainage, Hastings

Drainways|Timeline
Wastewater

Park Road Rising Main, Hastings

Drainways|Timeline
Subdivision

Gracelands Retirement Village, Hastings

Drainways|Timeline
Subdivision

West Place Subdivision, Greenmeadows

To find out more or you have a project requiring our expertise, then get in touch today