/ Timeline

/ Current Project

Ryman Retirement Village
Havelock North

The following timeline shows the on-going progress of one of our current projects and our approach to the job.

2019

Project start
20 Sep

image
20/09/2019: Site entry being established

Overview of site
26 Sep

image
26/09/2019: Overview of site in first month.

Haul roads being established
1 Oct

image
01/10/2019: Haul roads being established and main building being excavated for pre-loading.

First site office
4 Oct

image
04/10/2019: First site office and carpark established.

Stormwater materials
4 Oct

image
04/10/2019: Stormwater materials on site and starting to be installed.

Stormwater detention tanks installed
19 Oct

image
19/10/2019: First of 3 Triton Stormwater Detention Tanks being installed.

Main building pre-load
19 Oct

image
19/10/2019: A good start to the pre-load for the main building.

Pre-load progress
7 Nov

image
07/11/2019: Further Progress on the pre-load.

First building pads
7 Nov

image
07/11/2019: At the other end of the site – the first building pads being completed.

Building pads progressing
20 Nov

image

20/11/2019: South end of the site – services and building pads progressing well.

.

Main building pre-load complete
28 Nov

image
28/11/2019: 20,000m3 of pre-load material completed on the main building and pre-load on apartment block underway.

Several pads completed
9 Dec

image
09/12/2019: Several building pads completed ready to be handed over to builders.

Pre-load on main building complete
9 Dec

image
09/12/2019: Pre-load on main and apartment building complete, building pad preparation on 2nd apartment block well underway.
2020

First frames standing
14 Jan

image
14/01/2020: First frames standing and several building pads ready to box.

Overview of site
14 Jan

image
14/01/2020: First frames standing and several building pads ready to box.

From North to South
14 Jan

image
14/01/2020: Overview of site looking from North to South.

North building pads started
22 Jan

image
22/01/2020: More building pads being started at North end of site.

North end drainage
30 Jan

image
30/01/2020:  Building pads and drainage being completed at North end of site.

South end progress
30 Jan

image
30/01/2020: Plenty of action at the south end of the site.

Permanent site office
18 Feb

image
18/02/2020: Permanent site office compound established and civil drainage happening at North end of site.

Main building pre-load removal
18 Feb

image
18/02/2020: Pre-load on main building starting to be removed.

Apartment building pre-load removal
19 Mar

image
19/03/2020: Birds eye view of complete site, pre-load removed from apartment building.

Kerbs starting at South end
18 Jun

image
18/06/2020: Kerbs starting at south end of site.

North end house pads
18 Jun

image
18/06/2020: Meanwhile more house pads being prepared at north end of site.

Kerbs and roading underway
9 Jul

image
09/07/2020: Kerbs and roading underway, all services to townhouses being installed and gardens planted.

Kerbs and roading completed
7 Aug

image
07/08/2020: Roading, kerbs, topsoil, sub-soil drains being completed.

First asphalt down
15 Sep

image
15/09/2020: First asphalt down, more topsoil and roading happening.

South end complete
19 Oct

image
19/10/2020: South end of the site complete with grass, irrigation paving, planting and residents living in their homes.